Required conditions during real demand
Use equipment and qualified product / cleaning requirements at realistic production overlap. Define source and point-of-use conditions with synchronized time records; daily totals can hide constraining peaks.
New packages or operating losses expose unstable air, power or water interfaces, and source expansion is proposed before distribution and point-of-use conditions are measured.

Start with the business outcome
New packages or operating losses expose unstable air, power or water interfaces, and source expansion is proposed before distribution and point-of-use conditions are measured. Use qualified electrical, pressure-system and water / process specialists to separate source, distribution, controls and actual concurrent demand. Define each new package’s operating and startup conditions before selecting infrastructure. DPS can connect the process basis, capital alternatives, field / supplier interfaces, controls and project execution so the owner can make a reviewable investment decision.
DPS publishes utility-related engineering and installation scope. Specialist source packages, refrigerant / pressure-system work, electrical design, process water and local approvals require explicit qualified parties. No universal energy saving or capacity uplift is claimed.

Use equipment and qualified product / cleaning requirements at realistic production overlap. Define source and point-of-use conditions with synchronized time records; daily totals can hide constraining peaks.
Review routes, restrictions, insulation, control behavior and return duty alongside the utility source. Assess recovery between events and source redundancy according to the owner’s actual operating requirement.
Compare sequencing / distribution corrections with source expansion using metered baseline cost, tariff, added service, useful output, civil / electrical work and production interruption on equal scope.
Compare source, use point, return and production state during the actual event.
Assess feasible event timing, loss correction, controls and recovery without compromising qualified conditions.
Specify new equipment and infrastructure only after the delivered duty and future envelope are clear.
Swipe horizontally to compare all columns ↔
| System | Operating duty | Relevant DPS guide | Confirm before purchase |
|---|---|---|---|
| Utility design basis | Integrate actual process / CIP demand and interfaces. | Utilities & infrastructure ↗ | Qualified thermal / electrical / pressure / water scope. |
| Control and instruments | Trend and coordinate states, requests and recovery. | Automation & controls ↗ | Test conditions, alarms and supplier ownership. |
| CIP interface | Map cleaning source / supply / return and peaks. | CIP systems ↗ | Product soils, installed circuit and verification basis. |
| Field integration | Connect new or retained services in live areas. | Installation & integration ↗ | Civil / electrical / isolation / commissioning boundaries. |
Capture point-of-use pressure / flow and quality where applicable, electrical demand / starting events and water conditions with synchronized production states. Tariff demand charges and service lead time may affect the owner’s economics.
Swipe horizontally to compare all columns ↔
| Decision area | Operating / site evidence | Acceptance or responsibility |
|---|---|---|
| Compressed air | Required quality, peak flow, pressure loss and leakage. | Acceptance at the equipment demand. |
| Electrical service | Running / starting load, demand and protection interfaces. | Qualified design and supply feasibility. |
| Process water | Required quality, supply conditions, flow and return / drain. | Site- and product-specific service basis. |
| System alternative | Leak / distribution / sequence correction versus new source. | Installed cost, tariff, service and outage boundaries. |
Swipe horizontally to compare all columns ↔
| Observed condition | Measure before design | DPS / team decision | Economic basis |
|---|---|---|---|
| Compressed air | Required quality, peak flow, pressure loss and leakage. | Acceptance at the equipment demand. | Use the matched product / site baseline and the agreed counterfactual. |
| Electrical service | Running / starting load, demand and protection interfaces. | Qualified design and supply feasibility. | Include complete capital and one-time transition cash. |
| Process water | Required quality, supply conditions, flow and return / drain. | Site- and product-specific service basis. | Count only independent cash costs actually avoided or useful sold output. |
| System alternative | Leak / distribution / sequence correction versus new source. | Installed cost, tariff, service and outage boundaries. | Separate recurring operating benefit from one-time project exposure. |
Use qualified electrical, pressure-system and water / process specialists to separate source, distribution, controls and actual concurrent demand. Define each new package’s operating and startup conditions before selecting infrastructure.
Capture point-of-use pressure / flow and quality where applicable, electrical demand / starting events and water conditions with synchronized production states. Tariff demand charges and service lead time may affect the owner’s economics.
Compare proposals with the same product duty, supplier boundaries and acceptance basis. The amount below is a transparent planning example, not a market price range, supplier estimate or DPS quotation.
| Cost bucket | Assumed amount |
|---|---|
| Survey, measured baseline and engineering | $49,000 |
| Defined equipment / interface components | $112,000 |
| Field mechanical / electrical installation | $87,500 |
| Controls and instrument interfaces | $49,000 |
| Commissioning / qualified test support | $35,000 |
| Training, records and closeout | $17,500 |
| Defined project scope | $350,000 |
| Separate site / facility additions | $100,000 |
| Capital contingency (15%) | $67,500 |
| Separate one-time startup / shutdown cost | $35,000 |
| Incremental working capital | $10,000 |
| Total initial cash | $562,500 |
The defined scope assumes applicable freight, procurement charges and taxes are included in the owner’s estimate. Add missing civil, land / shell, OEM, environmental, validation and permitting costs explicitly. Site and field conditions, duty, production access and quoted supplier scope determine actual price. Financing is excluded.
Hypothetical case for compressed air electrical power and water constraints at food equipment: 250 days × 0.4 useful hour/day × 1,000 accepted kg/h × 65% realization gives 65,000 kg potential extra sales; the 80,000 kg demand ceiling yields 65,000 sold kg/year. Net price $4.20 less $2.70 incremental variable cost gives $1.50/kg contribution. Separately verified baseline energy / cleaning / maintenance assumptions are $68,000/year; actual paid-hour avoidance is $0/year. Added fixed operating cost is $18,000/year, and year-one gross benefit realizes at 75%. These values are original owner-planning assumptions, not supplier prices or a customer result.
Calculated from these assumptions: steady annual net benefit $147,500; year-one net cash $106,125; cash payback 4.09 years; five-year NPV at 10% is −$40,973. Change the assumptions below to test a different case.
Replace the illustrative inputs with your own measured or quoted values. The five-year pre-tax model uses good kilograms, demand-capped contribution and separately verified baseline savings; it is not a project quotation.
All defaults are illustrative. The default case is an operating-plant improvement, not a greenfield quote. For a new operation, set baseline savings to zero and enter every additional operating and capital cost.
Includes contingency, startup and working capital
Incremental operating cash before tax
Includes year-one ramp assumption
At 10% annual discount
Net annual benefit ÷ initial cash
Net cumulative gain ÷ initial cash
Modeled incremental sales: 65,000 kg/year at $1.50/kg contribution. The base case does not recover the required discounted return within five years. Year-one net cash: $106,125.
Realization needed for the target operating payback
67.5%
Minimum capacity realization for a 4-year operating cash payback; terminal recovery excluded. Demand and unit margin must also hold.
CSV export is local. No inputs are submitted.
Swipe the chart to compare all five years ↔
Swipe horizontally to compare all columns ↔
| Year | Net cash | Cumulative cash | Discounted cash |
|---|---|---|---|
| Initial | −$562,500 | −$562,500 | −$562,500 |
| Year 1 | $106,125 | −$456,375 | $96,477 |
| Year 2 | $147,500 | −$308,875 | $121,901 |
| Year 3 | $147,500 | −$161,375 | $110,819 |
| Year 4 | $147,500 | −$13,875 | $100,744 |
| Year 5 | $147,500 | $133,625 | $91,586 |
Swipe horizontally to compare all columns ↔
| Case | Annual benefit | NPV | Cash payback |
|---|---|---|---|
| Downside | $108,500 | −$283,450 | Beyond 5 years |
| Base | $147,500 | −$40,973 | 4.09 years |
| Upside | $173,338 | $51,100 | 3.52 years |
Downside: installed and site costs +20%, realization ×0.75 and unit contribution reduced by 20% of its absolute value. Upside: realization ×1.15, capped at 100%, and unit contribution improved by 10% of its absolute value. The demand ceiling still applies.
Initial cash = (defined project scope + site additions) × (1 + contingency) + separate startup / shutdown cost + working capital. Contingency is conservatively treated as spent initially.
Sold incremental kg = min(days × recovered hours/day × constrained good kg/hour × realization, incremental demand). Contribution = sold incremental kg × (net price − incremental variable cost). New-volume labor, energy and packaging belong in that variable cost.
Baseline material benefit uses the verified percentage of actual purchases avoided at unchanged accepted baseline output. It is not a direct subtraction of two loss rates. Count a recovered kilogram once, either as its applicable cash saving or as incremental contribution.
Net annual benefit = contribution + independently realized baseline cash savings − added fixed operating cost. Year one scales gross benefits by the ramp factor while paying the full added fixed operating cost. Do not also count the same launch loss in the one-time startup amount.
Cash ROI = net annual benefit / initial cash. Five-year net ROI = (five-year cash inflows − initial cash) / initial cash. NPV = −initial cash + Σ cash flow(t)/(1 + discount rate)^t. Payback uses annual cash with linear interpolation within the recovery year. The threshold solver excludes terminal working-capital recovery.
This is a five-year screening horizon, not an asset’s entire life. No tax, debt, depreciation, grants, escalation, asset resale or additional replacement capital is modeled. Include recurring service costs in operating expense and use a detailed monthly budget for formal capital approval.
Default gross saving is 5,000,000 kWh × 10% × $0.12 = $60,000/year, the main energy field. This narrow worksheet deducts $6,000 service to show $54,000 net; that $6,000 is included within the main $18,000 added fixed operating cost and must not be deducted twice.
Use representative products, measured constraints and a documented utility / cleaning envelope. Assign each supplier and owner interface.
Plan FAT / SAT, instruments, recipes, permissives, quality checks and upstream / downstream handshakes as appropriate to the scope.
After stabilization, compare matched products and operating conditions. Reconcile extra output with sales, and baseline savings with actual purchases, bills and payroll.

Published scope / project context
DPS publishes food / beverage project, process, utility, installation and controls context. Those materials establish relevant delivery disciplines. None of the amounts, recovered time, energy reductions, schedules or payback in this original screening example is attributed to a customer case.
Swipe horizontally to compare all columns ↔
| Decision | Targeted intervention | Broader replacement / new operation |
|---|---|---|
| Constraint | A measured gap can be corrected within retained assets. | The verified operating envelope cannot meet product, demand or reliability needs. |
| Cost scope | Include engineering, interfaces, shutdown, commissioning and retained-asset risk. | Include all new systems, site / facility work, OEMs, utilities, ramp and working capital. |
| Benefit | Only incremental contribution and genuinely avoided costs versus the current operation. | Demand-supported contribution less the full additional operating cost versus the agreed alternative. |
| Acceptance | Verify the changed duty and its effect on the complete line. | Verify the integrated new train and the owner’s readiness to operate. |
Prepare the information below, export the assumptions you have modeled, and discuss the unknowns with DPS. An unmeasured input is a question to resolve, not a reason to invent precision.
Checklist and model data stay in this browser until you choose to share them.
The DPS manufacturing-scenarios overview and linked service descriptions support engineering / integration context. The site-specific findings, illustrative financial assumptions and decision register on this page require project assessment; they are not published DPS customer results.
Guide assumptions reviewed on 26 October 2026. Qualified site / product teams establish regulatory and food-safety requirements; this guide does not prescribe a validated process.

Define a food plant utility design basis using operating events, simultaneous peaks, supply conditions, future capacity and clear package interfaces.

Compare utility peak capacity, sequencing and buffers using a timed load model, DPS CIP interfaces and a reported retrofit case with staged tie-ins.

Confirm utility availability before buying land: required conditions, provider evidence, connection scope, upgrade responsibilities and decision deadlines.