Case Study • Meat Processing

Confidential Client
Ground Beef Line Execution

350,000 lbs/week line in just 6 months

Rapidly engineered, permitted, and installed to minimize downtime. Strategic development allowed lower rate production to proceed key weeks before full commissioning, creating early client return.

Fast-Track Turnkey Execution Timeline
Active Line
Active ground beef packaging line integration
Revenue at
Wk 11 Active
Complex Facility Setup
Live operational retrofits based in LA
12 Trade Contractors
Simultaneously synchronized by DPS
Minimized Interuption
Only 4 weeks cumulative downtime
Revenue Extraction
Activated key production early

Critical Timelines • High Performance Results

350K lbs
Beef Volume Weekly
Substantial volume increase with clean room slicing, loading and sealing integration.
6 Mos
Turnkey Execution
All permitting, structural updates, mechanical placement, and utility alignment.
4 Wks
Downtime Contained
Ongoing commercial deliveries remained prioritized with minimal offline impact.
Wk 11 Go
Early Production
Lower-rate operations deployed weeks ahead of full validation checklist completion.

The Challenge: Installing High-Volume Capacity in Concurrently Running Facility

The client required a major capacity expansion inside an existing, highly active Los Angeles manufacturing plant with a target of installing a massive 350,000 lbs/week high-capacity ground beef processing line.

With peak sales season looming, shutting down operational segments was out of the question; cumulative production timeline disruptions could not exceed four weeks. Fire protection codes, local permits, and physical mechanical moves had to occur concurrently while other lines maintained volume.

! Project Restraints
  • Compressed Schedule — Hard 6-month turnkey delivery limit.
  • Uninterrupted Flow — Maximum 4 weeks total production downtime.
  • Live Plant Coordination — Clean layout boundaries in continuous utilization.
  • Complex Inspections — Fire suppression loops and alarm integrations.
Turnkey DPS Solution

DPS purchased critical-path equipment immediately. Completed structural, mechanical, electrical, plumbing, and architectural layouts in just 4 weeks, with a dedicated task force directly organizing 12 subcontractors.

Design • Build • Manage – Dynamic Alignment

D
Stage One

DESIGN

All disciplines engineered within 4 weeks. Key process assets ordered first to eliminate logistics delivery lag. Fully reconciled fire suppression system within existing layout parameters.

B
Stage Two

BUILD

Turnkey field representation managing 12 specialty contractors. Handled processing room relocations, slab adjustments, utility piping hooks, and sanitation boundary walls cleanly.

M
Stage Three

MANAGE

Focused project management with weekly dashboarding logic. Designed and activated phased production by Week 11, giving the client early market capitalization months before baseline closeout.

EXECUTION TIMELINE

Phased Relocation & Capacity Delivery Timeline

Turnkey Delivery Completion
Weeks 1–4

Engineering & Permits

Structural, MEP designs calculated. Immediate equipment acquisitions placed. Approvals fully released in Los Angeles county.

Weeks 5–10

Installation & Retrofit

Under-floor utility trenches cut, process pipes distributed. Line assets positioned and existing processing room relocated elegantly.

Week 11 🎉

Early Production

Relocated slicing room delivered. Early lower-rate operations initialized to protect active product supply goals.

Weeks 12–20

Full Integration

Fire prevention safety nets run, complex control calibrations finished and SCADA systems certified with only 4 weeks operational gap.

Month 6

Full Scale Achieved

Ground beef line running at maximum 350,000 lbs/week layout with zero delay or supply defaults reporting.

CLIENT VOICE
“DPS delivered our ground beef line faster than any partner we’ve ever worked with. The early production at week 11 allowed us to capture peak season sales we would have otherwise missed.”
MC
Operations Director Confidential Client — Leading Meat Processor
Performance Highlights
Total physical downtime Only 4 weeks
Early revenue generated Week 11
Coordinated subcontractors 12 Trades

Connect With our Turnkey Plant Architects

Let’s map out how DPS can deliver your next processing installation, equipment retrofit, or complex meat facility expansion with matching timeline security and minimized downtime.