Case Study • Food & Beverage Retail

Albertsons
CIP System & Air Farm

State-of-the-Art System installed with zero unplanned downtime

Completed cleanly in exactly three brief outages. Detailed offsite prefabrication and strategic scheduling allowed full replacement with zero unplanned disruptions.

Fast-Track Turnkey Execution Timeline
Active Line
Active Clean-In-Place piping system integration
Outages Completed
3 Outages
Active Plant Setup
Live Albertsons production operations
Surgical Accuracy
Engineered offsite preassembly stages
Contained Outages
All cuts conducted under 4 hours
Continuity Achieved
100% operational throughput preserved

Critical Timelines • High Performance Results

3 Outages
Completed Outage Count
All installation phases achieved sequentially via three planned interruptions.
<4 Hrs
Maximum Planned Outage
Strict deadline control applied to ensure zero material or manufacturing delays.
0 Disruption
Unplanned Interruption
Facility preserved full commercial continuity with zero margin of error allowed.
100% Go
Continuity Maintained
Sanitized delivery lines fully active with next-generation utility systems online.

The Challenge: Replace Critical CIP and Air Systems with Virtually Zero Downtime

Albertsons required a major utility modernization at their active production plant. They needed to fully replace aging Clean-In-Place (CIP) assets and optimize their foundational pneumatic Air Farm infrastructure.

At a high-volume retail supply facility, taking main production systems offline would cost substantial volume. DPS had only three planned outage windows, none of which could exceed four hours under any situation. Perfect, fast validation of connections was the key requirement.

! Project Restraints
  • Outages strictly limited — Absolutely three brief cuts allowed.
  • Time limits enforced — Strictly max 4 hours per window.
  • Running operations — Standard dairy and food flow active.
  • Hygienic conditions — Stringent clean room and valve codes applied.
Turnkey DPS Solution

DPS engineered, prefabricated, and staged all piping manifolds off-site. Meticulous planning of every process step, back-up system, and utility swap protected active product supply lanes seamlessly.

Design • Build • Manage – Dynamic Alignment

D
Stage One

DESIGN

Detailed pre-planning and 3D modeling. Piping and valve matrixes modeled off-site to match plant ports perfectly and compress on-site structural modifications.

B
Stage Two

BUILD

Field prefabrication of manifolds, skid frames, and air conduits. Real-time physical rigging sequences pre-drilled to ensure connection drops were completed cleanly under deadline pressures.

M
Stage Three

MANAGE

Strict execution checklists tracking minute-by-minute progress. Successfully completed all three tie-ins on budget and ahead of time, ensuring Albertsons maintained full market operation with zero supply disruptions.

EXECUTION TIMELINE

Phased Modernization & System Integration

Turnkey Delivery Completion
Pre-Outage

Engineering & Prefabrication

Offsite fabrication of CIP skids. Material procurement set and local field resources fully mobilized.

Outage 1

< 4 Hours

First tie-in completed. Primary CIP lines cut over and initial process piping validations released cleanly.

Outage 2

< 4 Hours

Air Farm manifolds integrated and pneumatic line pressure checks executed concurrently without delay.

Outage 3 🎉

< 4 Hours

Final integration loop finalized. System validation and dry run cycles safely completed inside the final planned limit.

Post-Outage

Full Integration

New utilities running at full commercial capacity with 100% operational supply chain maintained.

CLIENT VOICE
“DPS executed this critical upgrade with incredible precision. We experienced zero unplanned downtime across three separate outages. Every minute truly counted — and they delivered.”
A
Facilities Engineering Manager
Albertsons Companies
IMPACT HIGHLIGHTS
Total Outages Scheduled 3 (all < 4 hrs)
Unplanned production loss Zero
Piping Integration efficiency 100% Successful

Connect With our CIP Upgrade Architects

Let’s map out how DPS can deliver your next facility modernization, line expansion, or complex process plant retrofit with absolute timing precision and zero commercial lag.

Confidential Engineering Feasibility Request