Design-Bid-Build vs Design-Build for Food Facilities in the United States

Food and beverage manufacturers in the United States rarely choose a project delivery method based on theory alone. They choose it based on throughput goals, startup deadlines, utility constraints, food safety risks, and the financial reality of getting a plant online without damaging margins. Whether a company is expanding a protein line in Arkansas, installing aseptic capacity in California, relocating equipment in Texas, or building a co-packing operation near Chicago, the decision between design-bid-build and design-build can materially affect capital efficiency, launch timing, and operational reliability.

This guide explains the practical differences between the two methods for U.S. food facilities. It is written for owners, operations leaders, finance teams, plant engineers, and procurement groups evaluating processing expansions, utility upgrades, greenfield projects, retrofits, and compliance-driven improvements. The focus is not only on construction mechanics, but also on how delivery structure influences food safety, production continuity, change orders, and accountability across the life of the project.

Fast Take

If you need the short answer, design-build is usually the stronger option for fast-moving food and beverage projects in the United States because engineering, procurement, construction, and coordination are aligned under one lead entity. That often means fewer handoff gaps, earlier cost feedback, better schedule control, and less owner burden during execution.

Design-bid-build can still be the right choice when an owner wants a fully developed design before construction pricing, has internal technical resources to manage multiple parties, or must follow procurement rules that require a traditional competitive bid structure. It is often used by organizations that prefer a clear separation between designer and builder or need a rigid public-style procurement process.

For food facilities specifically, the best method depends on six core realities:

  • How quickly capacity must come online
  • How sensitive the project is to shutdown windows
  • How complex the process and utility integration are
  • How likely the scope is to evolve during design
  • How much internal owner oversight is available
  • How important food-industry compliance knowledge is to execution

In many U.S. food projects, especially brownfield work with active production, owners prefer integrated delivery because process, controls, utilities, sanitary design, and installation sequencing must work together from day one. That is why many manufacturers near logistics hubs such as Dallas-Fort Worth, the Port of Savannah, the Inland Empire, Minneapolis, and the I-95 corridor are shifting toward delivery teams that can engineer, build, and manage under a single commercial framework.

Decision FactorDesign-Bid-BuildDesign-BuildWhat It Means for Food Plants
Single point of responsibilityNoYesImportant when process, utilities, and construction must stay aligned
Early cost visibilityModerateHighHelps owners protect capital budgets before equipment commitments
Schedule overlapLimitedStrongUseful for urgent capacity expansions and shutdown work
Owner coordination burdenHigherLowerMatters when internal teams are lean
Change order exposureUsually higherOften lower when scope is well managedCritical in retrofits with hidden field conditions
Best fitFully defined scope, formal bid environmentSpeed, integration, complexityMany food and beverage projects favor this path

The table above simplifies the issue, but it captures the core reason this choice matters: food facilities are not generic buildings. They combine process piping, sanitary design, refrigeration, steam, compressed air, water treatment, CIP, automation, and regulatory requirements. Delivery method affects how well those systems come together.

Understanding Project Delivery Methods

In a design-bid-build model, the owner first hires a designer or engineer to develop the project documents. Once the plans and specifications reach a sufficient level of completion, contractors bid the work, and the owner awards construction separately. The owner effectively sits in the middle of the designer and the builder. That structure can offer clear procurement stages, but it also creates more interfaces to manage.

In a design-build model, one lead entity is responsible for both design and construction, either directly or through managed partners. Engineering and field execution are coordinated earlier. Procurement decisions can begin before every drawing is 100 percent complete, and constructability input enters the design process sooner. For food manufacturers, this often improves equipment layout decisions, utility tie-ins, sequencing, and commissioning planning.

The market context in the United States supports this shift. Manufacturers are adding lines closer to end markets, responding to labor shortages with automation, and increasing resilience after supply-chain disruptions around ports such as Los Angeles/Long Beach, Houston, and New York/New Jersey. At the same time, sustainability goals, wastewater constraints, and stricter food safety expectations are making projects more interdisciplinary. Traditional linear delivery still works, but integrated delivery is increasingly favored where timing and coordination matter more than lowest first-cost bidding alone.

Different product categories also influence the decision. Beverage plants often require precise integration among blending, carbonation, filtration, pasteurization, batching, controls, and packaging interfaces. Protein and prepared food plants face washdown demands, hygienic zoning, thermal processing, refrigeration, and USDA concerns. Dairy and aseptic operations add another layer of validation and utility reliability requirements. The more connected the systems are, the more valuable delivery integration becomes.

The chart illustrates a realistic market trend: more U.S. food and beverage capital projects are moving toward integrated delivery as schedule risk, labor scarcity, and process complexity increase. This does not eliminate design-bid-build. It simply means owners are becoming more selective about when they use it.

Project TypeTypical U.S. ExampleBetter Fit: Design-Bid-BuildBetter Fit: Design-BuildReason
Greenfield beverage plantCo-packer near Atlanta or PhoenixPossibleStrongHigh need for utility and process coordination
Protein line expansionPoultry facility in ArkansasModerateStrongShutdown planning and sanitation sequencing are critical
Utility replacementBoiler or glycol upgrade in WisconsinGoodGoodChoice depends on complexity and downtime tolerance
Warehouse additionDry storage in OhioStrongModerateLess process integration required
Aseptic retrofitCalifornia dairy beverage plantWeakStrongValidation, process controls, and utility integration matter
Regulatory compliance upgradeUSDA washdown improvements in NebraskaModerateStrongField conditions and operational continuity drive value

This comparison matters when buying services. Owners should not ask only, “Which method costs less?” They should ask, “Which method best protects startup date, production continuity, quality, and long-term profitability?” For a refrigerated plant in the Midwest or a sauce facility near Memphis, a two-week delay may cost more than the entire perceived savings from a low-bid approach.

Cost Structure Analysis

Cost is where many project teams start, but too many discussions focus only on first-cost pricing. In practice, U.S. food manufacturers should evaluate cost structure, not just bid amount. Design-bid-build may appear less expensive up front because design fees and construction fees are separated and competitive bidding can create visible price pressure. However, that apparent savings can erode if drawings are incomplete, field coordination is difficult, or scope changes appear after bid.

Design-build often provides earlier budget alignment because the design and construction team can price materials, labor, and installation approaches while engineering is still progressing. That does not mean it is always cheaper on paper. It means cost feedback enters sooner, allowing the owner to make capital decisions before details become expensive to change.

For food projects, hidden costs often appear in five places: utility tie-ins, sanitary piping details, controls integration, phased installation around production, and startup/commissioning. These are exactly the areas where fragmented project delivery can create budget drift. If the engineer assumes one installation approach and the contractor discovers another is required in the field, the owner often pays for the gap.

Cost CategoryDesign-Bid-Build PatternDesign-Build PatternOwner Risk
Design feesSeparate contractBundled or coordinatedScope misalignment if design assumptions change
Construction pricingAfter design milestone or completionProgressive during designLater discovery of budget gaps in DBB
Value engineeringOften late-stageEarlier and more practicalLate redesign can increase total spend
General conditionsCan extend with schedule driftOften controlled through integrated sequencingLonger field duration raises indirect costs
Change ordersMore frequent in fragmented scopesUsually fewer with aligned responsibilityBudget unpredictability affects ROI
Commissioning/startupMay be split across firmsMore centralizedDelayed startup becomes a hidden capital cost

The table shows why finance teams should compare total installed cost and startup confidence, not just initial contractor pricing. A dairy producer in Idaho or a spirits operation in Kentucky may discover that the cheaper-looking option creates more commercial exposure once validation, downtime, and missed production are included.

Another major cost driver is procurement timing. Long-lead items such as boilers, compressors, heat exchangers, controls panels, stainless vessels, retort systems, or refrigeration components can shift a project budget if ordered too late. Integrated delivery allows the team to release procurement packages sooner, reducing escalation risk. This has been especially relevant in the United States since supply chain volatility increased lead times for electrical gear, stainless fabrication, and automation hardware.

Owners should also assess soft-cost burden. In design-bid-build, internal staff often spend more time managing RFIs, reconciling designer and contractor interpretations, and negotiating responsibility for field changes. That time has a cost, especially for lean operations groups already focused on production. In contrast, a strong design-build team can reduce the owner’s coordination load and allow management to stay focused on operations and commercial goals.

Schedule Control Comparison

Schedule is often the deciding factor in food facility capital planning. If a plant needs output for a new customer launch, a seasonal production window, or a packaging transition, the value of time can outweigh modest differences in direct construction cost. In the United States, many food and beverage manufacturers are working around retailer resets, harvest cycles, contract pack commitments, and freight network realities. Schedule reliability is therefore a strategic issue, not just a project-management metric.

Design-bid-build follows a more linear sequence. Design must advance far enough before bid, and construction generally begins after contract award. This method can work well for straightforward scopes with ample time. The challenge is that delays in design push bidding, procurement, and field work downstream. Any redesign after bid can disrupt the entire schedule.

Design-build compresses the timeline by overlapping activities. Early demolition packages, utility relocations, equipment pad work, and long-lead procurement can begin while later design packages continue. That overlap is especially useful in operating facilities where production windows are narrow. For example, a sauce plant near St. Louis may need utility tie-ins over holiday shutdowns, while a beverage site in North Carolina may need tank and piping installation completed before summer demand peaks.

Schedule ElementDesign-Bid-BuildDesign-BuildOperational Impact
Design-to-field handoffSequentialOverlappingDB can reduce idle time between phases
Constructability reviewLaterEarlierLess field rework in integrated teams
Long-lead procurementUsually laterCan start earlierProtects startup dates
Shutdown planningSeparate coordinationIntegrated planningBetter for active production facilities
Response to field conditionsSlower approvalsFaster internal alignmentReduces production disruption
Commissioning readinessMore fragmentedMore unifiedImproves ramp-up confidence

For manufacturers buying capital services, schedule control should be evaluated at the level of milestones that matter to the business: design freeze, equipment release, utility energization, mechanical completion, wet commissioning, product qualification, and commercial startup. A method that saves four weeks on paper but creates confusion during commissioning is not actually faster.

The bar chart highlights where fast-track delivery demand is strongest. Co-packing, beverage, and aseptic projects often move quickly because customer commitments and line integration drive compressed schedules. Protein and dairy are not far behind, especially where shutdown windows and sanitation requirements are tight.

By 2026, schedule management in U.S. food projects will be shaped by three additional trends: more digital coordination through 3D modeling and clash review, greater use of modular utility skids and fabricated process assemblies, and stronger owner expectations for predictive scheduling tied to procurement lead-time tracking. Delivery teams that cannot connect engineering decisions to installation sequencing will increasingly struggle to compete.

Risk Allocation Framework

Every project delivery method is really a method of assigning risk. The question is not whether risk exists, but who controls it, who prices it, and who pays when reality differs from assumptions. For U.S. food facilities, the most important risks typically include incomplete design, hidden existing conditions, utility capacity gaps, sanitation and zoning errors, startup underperformance, and operational downtime.

In design-bid-build, risk is distributed across separate contracts. The designer owns design services, the contractor owns construction means and methods, and the owner often becomes the party that bridges interpretation gaps between them. When disputes arise over whether a field condition was shown, implied, or reasonably inferable, the owner may absorb delay and management burden even if costs are eventually allocated elsewhere.

In design-build, more risk can be consolidated under a single lead entity. That simplifies accountability, though only if the contract is written well and the scope definition is disciplined. Owners should still pay close attention to exclusions, assumptions, performance criteria, and who owns specialty equipment interfaces. A single point of responsibility is valuable only when it is real, not cosmetic.

Risk ItemDesign-Bid-Build Typical Owner ExposureDesign-Build Typical Owner ExposureFood Facility Example
Design coordination gapsHighLowerPipe routing conflicts with existing process lines
Cost escalation before awardHigherLower to moderateElectrical gear pricing moves during final design
Existing condition surprisesModerate to highModerateUnknown slab reinforcement or undersized utilities
Schedule slippageHigherLower when managed wellMissed shutdown window in active plant
Commissioning disputesHigherLowerControls, equipment, and utilities fail to align
Food safety noncomplianceDepends heavily on consultant qualityLower with specialized teamDrainage, zoning, or hygienic design issues

The explanation behind this table is straightforward: risk follows fragmentation. The more parties and handoffs involved, the more room there is for assumptions to diverge. That does not make design-bid-build wrong; it means owners need stronger internal governance when using it.

Buying advice for U.S. manufacturers is to evaluate risk in business terms. If a missed startup costs $250,000 per week in lost contribution margin, that number should shape the delivery decision. If a brownfield installation threatens USDA operations or customer audit readiness, the cost of coordination failure may far exceed any bidding advantage.

Future policy trends also matter. By 2026, owners should expect continued pressure around water use, wastewater discharge, energy efficiency, electrification planning in some regions, refrigerant management, and documentation tied to food safety systems. Projects near heavily regulated markets such as California, New Jersey, and parts of the Pacific Northwest may face more compliance coordination than they did several years ago. Integrated teams with engineering and construction alignment are often better positioned to absorb that complexity.

Contract Administration Differences

Contract administration is where delivery method differences become visible every week. Submittals, RFIs, meeting cadence, payment approvals, schedule updates, and responsibility mapping all change based on whether the owner manages separate design and construction contracts or works through a single integrated lead.

Under design-bid-build, the owner usually administers multiple primary relationships. Questions may flow from contractor to designer and back through the owner. If a process skid arrives with support requirements different from the issued structural drawings, the clarification path can be slow. This is manageable for experienced owner teams, but it adds administrative friction.

Under design-build, contract administration is often simpler for the owner because coordination occurs internally within the delivery team. That does not eliminate the need for governance. Owners still need clear reporting, milestone approvals, scope logs, and contingency visibility. But the owner typically spends less time refereeing technical disagreements.

This difference is especially relevant in food sectors where specialty equipment interfaces are critical. A brewery expansion in Colorado, a yogurt facility in upstate New York, or a prepared foods retrofit in Tennessee may involve stainless fabrication, controls logic, CIP integration, utility balancing, and live sanitation protocols. Contract administration works best when those issues are handled by a team built around operational execution rather than disconnected scopes.

Many U.S. owners now prefer project partners that can act beyond basic construction coordination. They want technical leadership, practical field management, and honest commercial guidance. That includes feasibility support, owner’s representation, procurement planning, and execution management tied directly to business outcomes. Those needs have helped grow models that combine engineering, construction oversight, and operational accountability instead of treating each function in isolation.

When evaluating providers, buyers should review sample reporting packages, change logs, schedule dashboards, and commissioning plans. Ask how the team manages local trade partners in markets such as Charlotte, Houston, Fresno, Omaha, and Grand Rapids. Ask how often cost forecasts are refreshed. Ask who owns final coordination among process, structural, mechanical, electrical, controls, and sanitary requirements. Good contract administration is not paperwork. It is the system that prevents small issues from becoming expensive delays.

Impact of Change Order Management

Change orders are often where the economic difference between delivery methods becomes obvious. In design-bid-build, changes can arise from incomplete drawings, unforeseen site conditions, owner scope revisions, long-lead substitutions, or coordination conflicts between specialty systems. Because responsibility is segmented, negotiation over cause and pricing can consume time and management attention.

In design-build, change orders do not disappear, but they are often easier to control when the team developed the design and construction plan together. If a utility route must move, the impact can be assessed in one integrated conversation instead of an owner-mediated debate between separate firms. The result is usually faster decision-making and fewer adversarial interactions.

Food plants are especially vulnerable to change-order growth because brownfield realities are rarely perfect. Existing drawings may be outdated. Drain slopes may not match assumptions. Utility capacity may be lower than expected. Packaging equipment suppliers may shift connection points. Sanitary zoning logic may need refinement after field review. The delivery structure determines whether these discoveries become manageable adjustments or recurring disputes.

The area chart shows a realistic industry trend: better early coordination is reducing the percentage of project value lost to late changes. This is one reason owners are leaning toward integrated execution models, especially when process, utilities, and controls are deeply interdependent.

To manage changes well, owners should require five things regardless of method:

  • A documented basis of design tied to production goals
  • Explicit scope assumptions and exclusions
  • Regular budget updates as design evolves
  • A formal decision log for owner-driven changes
  • Commissioning criteria agreed before installation starts

In practice, the best way to reduce change-order pain is early field verification and earlier builder involvement. Laser scanning, utility mapping, shutdown workshops, and equipment interface reviews all help. For U.S. manufacturers operating older plants in cities such as Newark, Baltimore, Milwaukee, or New Orleans, these steps can save significant time and money.

Food-Industry Contractor Expertise

Food-specific expertise is where many generic project comparisons fall short. A contractor or delivery team may understand industrial construction but still struggle with hygienic design, product flow, washdown environments, allergen segregation, clean utility requirements, thermal processing, or regulatory expectations. For food and beverage owners, this expertise gap can be more damaging than a modest pricing difference.

Consider the range of applications in the United States: brewing and fermentation, distilled spirits, wine, RTD beverages, soft drinks, juice, dairy beverages, aseptic filling, beef and pork processing, poultry, seafood, plant-based protein, sauces, prepared meals, dairy products, and shelf-stable retort operations. Each category carries different processing logic, utility loads, and compliance demands. Delivery teams that truly know the sector can identify bottlenecks before they become change orders or startup failures.

Technological capability matters first. Owners should look for teams that understand structural, mechanical, plumbing, electrical, process, and controls engineering together, not in isolation. In food facilities, PLC programming, automation architecture, SCADA visibility, batch control, and line integration can be just as important as concrete and steel. A team that can evaluate fermentation systems, pasteurization methods, distillation layouts, CIP logic, water treatment, refrigeration, and recipe control will usually make better project decisions earlier.

Manufacturing capability matters next. Many owners benefit from project partners that do more than broker third-party equipment. A firm with experience designing and supplying tanks, CIP systems, tumblers, cooking vessels, or other process assets can often coordinate fabrication and installation more effectively. This is especially useful when plant layout, sanitary routing, and startup sequencing must be optimized together.

Service capability matters just as much. The strongest food project partners typically combine process engineering, feasibility studies, capital planning, owner’s representation, project and program management, general contracting or equivalent field leadership, equipment supply, installation, and system integration. That broad service reach reduces handoff gaps and gives the owner clearer accountability from concept through commissioning.

This is one reason manufacturers across North America increasingly seek specialized firms rather than generalists when undertaking food and beverage capital projects. For example, food and beverage engineering services that combine process design with field execution are often more valuable than a conventional bidder list for complex operational projects.

Expertise AreaWhy It MattersQuestions to AskTypical Red Flag
Sanitary process designPrevents contamination and cleaning issuesHow do you handle CIP, drains, slopes, and hygienic zoning?Generic industrial experience with no food examples
Controls and automationRemoves bottlenecks and improves throughputCan you support PLC, SCADA, batch logic, and integration?Controls handled as an afterthought
Utility infrastructureSteam, glycol, air, and water drive uptimeHow do you size and phase utility upgrades?Underestimating tie-ins and redundancy
Equipment integrationReduces field conflicts and startup delaysWho coordinates OEM interfaces and installation details?Unclear ownership across vendors
Compliance fluencySupports FDA, USDA, SQF, and BRC readinessWhat audit-sensitive projects have you executed?No documentation discipline
Live plant executionProtects production during constructionHow do you plan shutdowns and sanitation barriers?No brownfield strategy

For buyers, local suppliers and trade networks also matter. A strong national project team should still know how to manage local electricians, pipefitters, refrigeration crews, and concrete contractors in each region. Labor conditions in Southern California differ from those in the Carolinas or the Upper Midwest. Permitting expectations in New Jersey differ from Texas. The best delivery partners combine national food expertise with reliable regional execution.

The comparison chart reflects a common market reality: general contractors may have broad field capacity, but specialized food project teams often outperform when compliance, process integration, and startup reliability are central to success.

For equipment-related projects, manufacturers should also review available food processing equipment capabilities to determine whether the project partner can align custom vessels, CIP systems, utility skids, and process hardware with the facility layout and commercial plan.

About Our Company

Disruptive Process Solutions, or DPS, approaches food and beverage projects as a business-minded capital partner rather than a conventional contractor. The company serves manufacturers across the United States and Canada, supporting both food and beverage operations with a model built around engineering the solution, building it through disciplined field execution, and managing the entire program so that the owner’s commercial objectives stay in focus.

From a technology standpoint, DPS supports complex process environments that include fermentation systems, distillation systems, pasteurization and sterilization technologies, aseptic processing, blending and batching, filtration, water treatment, dairy processing, retort systems, plant protein applications, refrigeration, steam, compressed air, controls, and SCADA-driven automation. That breadth matters because food projects rarely fail due to one isolated component; they fail when systems are not coordinated.

From a manufacturing standpoint, DPS also brings equipment capability to the table, including its own branded process equipment such as tanks, custom CIP systems, tumblers, and cooking vessels. For owners, this can create a tighter connection between engineered intent and installed reality, especially on projects where custom process hardware is central to throughput or sanitation performance.

From a service standpoint, DPS delivers process engineering, feasibility support, owner’s representation, project and program management, general contracting where licensed, field coordination elsewhere through equivalent managed execution, equipment supply, installation, and system integration. That broad scope helps reduce the disconnect that often appears between planning and execution.

The firm is intentionally lean and agile, with leadership structured for fast decision-making and project-based execution. This is useful for clients who need direct communication, candid advice, and quick technical resolution rather than bureaucratic layers. DPS is especially well suited for manufacturers that value transparency, long-term profitability, and honest recommendations, even when the best advice is to spend less capital than originally planned.

One of the practical reasons owners engage DPS is its willingness to challenge assumptions when economics or operations do not support the planned spend. That approach aligns with the company’s focus on profitable projects rather than simple project volume. Manufacturers interested in the company’s background can learn more on the about DPS page, and those evaluating execution examples can review selected project case studies.

For U.S. food and beverage producers, the value of a partner like DPS is not only technical capability. It is the ability to connect capital planning, process design, field execution, and startup outcomes into one accountable operating model. In an environment where labor is tight, customer timelines are unforgiving, and margins are under pressure, that alignment is increasingly valuable.

Frequently Asked Questions

1. Which method is usually faster for a U.S. food plant project?
Design-build is usually faster because design, procurement, and construction can overlap. That is especially important for line additions, utility upgrades, and shutdown-driven work in active food plants.

2. Is design-bid-build always cheaper?
Not necessarily. It may look cheaper at bid time, but total cost can rise through schedule drift, coordination gaps, and change orders. Owners should compare total installed cost and startup risk, not just first-cost pricing.

3. When does design-bid-build make sense?
It makes sense when scope is very well defined, schedule pressure is moderate, the owner has strong internal project management resources, or procurement rules require separated design and construction contracts.

4. Why is food-industry expertise so important?
Because food plants involve sanitary design, utility integration, automation, compliance, and production continuity. A contractor without food-sector experience may understand construction but still miss critical operational requirements.

5. What industries benefit most from integrated delivery?
Beverage, dairy, protein, aseptic, prepared foods, and co-packing all benefit, especially where process systems, controls, and utilities are tightly linked.

6. How should owners compare proposals?
Compare delivery structure, team food experience, schedule approach, assumptions, exclusions, change-order process, commissioning plan, and accountability for process-equipment interfaces.

7. What should be included in early planning?
Production goals, utility loads, hygienic zoning, regulatory requirements, shutdown windows, procurement lead times, automation needs, wastewater impacts, and a realistic startup plan.

8. What trends will matter most in 2026?
Expect more modularization, stronger digital coordination, increased automation, greater sustainability pressure, tighter water and energy scrutiny, and more owner demand for integrated delivery that protects both margins and speed to market.

9. How do local conditions affect the choice?
Regional labor markets, permitting pace, utility access, and proximity to ports or distribution corridors all matter. Projects near Los Angeles, Houston, Savannah, Chicago, and New Jersey often face different trade and logistics realities that can favor earlier coordination.

10. What is the best buying advice for U.S. manufacturers?
Choose the delivery method that best supports profitability, not just procurement optics. If the project is schedule-sensitive, process-heavy, or likely to evolve, integrated delivery often creates better business results than a fragmented low-bid path.

In the United States market, the design-bid-build versus design-build decision should be treated as a strategic capital choice. For simple, fully defined scopes, traditional procurement can work well. For complex food and beverage projects where speed, integration, and accountability drive value, design-build frequently offers the stronger path. The right answer depends on plant conditions, product type, internal resources, and how much risk the owner is prepared to manage directly.

Owners who evaluate delivery method through the lens of operations, not just construction, tend to make better decisions. They ask how the project will affect throughput, quality, utility resilience, staffing, sanitation, and time to revenue. In food manufacturing, those are the metrics that matter most.

[/trp_language]

Complete Company Portfolio

About the Author: Disruptive Process Solutions (DPS)

The DPS team combines process engineering expertise with real-world food and beverage manufacturing experience. Our content focuses on process optimization, production efficiency, facility improvements, and practical solutions that help manufacturers operate more effectively in a rapidly evolving industry.

Contact DPS Today